2MW Generator Solution for Water Treatment Plant

DELIVERED PROJECT

Table of Contents

Project details

Products and Services Included: 2MW Generator Solution for Water Treatment Plant

2x AP1000 Open Set generators, bespoke 2,000L Double skinned fuel tanks, Synchronise controllers using DSE8610MKII

Location: UK

Project overview

A leading UK Water Treatment Company approached Constant Power Solutions after finding us through our Bespoke Generator Solutions webpage. They required a reliable and robust backup power solution for one of their critical sewage treatment plants. The nature of their operations demanded a system that could offer high-capacity, continuous power in the event of a mains failure.

The client required two synchronised 1000kVA diesel generators (providing a total of 2000kVA), forming the heart of their backup system to ensure uninterrupted treatment processes at the facility.

Project scope

Planning

Instead of a traditional site visit, the client visited our CPS headquarters to collaborate on the design and project requirements. This face-to-face interaction facilitated detailed discussions and quick decisions, which were essential given the tight timeline.

CPS delivered a full turnkey design solution, working directly with the client to ensure every detail—from layout to system specifications met the site’s needs. Since the generators would be installed in a bespoke plant room, precise design was crucial.

We agreed on a lead time of 12-14 weeks, covering design approval, manufacturing, testing, and delivery.

Challenges

Managing the lead time was our most pressing challenge. With strict deadlines, we had to ensure designs were approved and sent to production without delays.

Additionally, the generator room presented spatial constraints. We had to ensure the entire system would fit and operate optimally in the confined space. By involving our design engineers early and coordinating closely with the client, we overcame these challenges successfully.

After-Sales Support

We hosted a Factory Acceptance Test (FAT) day, enabling the client to inspect and verify the system’s performance before dispatch. After the sale, we provided technical assistance during the installation phase, ensuring smooth operation on-site.

We continue to support the client to ensure the system runs reliably for years to come.

This project demonstrates our ability to deliver WIMES-compliant generator solutions tailored for the water industry. Whether for open or containerised systems, we pride ourselves on offering engineering-led, UK-manufactured power solutions for the most demanding applications.

Get in touch for more information on this 2MW Generator Solution for Water Treatment Plant!

Need Expert Help?

Contact us with your specification

Use the form below to tell us your requirements or to receive a call back from a member of the Constant Power Solutions team.

Translate »